Thursday 13 July 2023
Waterline Place, Williamstown, VIC.
Merchant Construction Update July 2023
Merchant apartments are making great progress and are currently on program:
- Hamilton Marino (HMB) is nearing the completion of the concrete structure of The Merchant with all floors to level 5 poured. Levels 6, 7 and the roof top are still expected to be complete in August as the builder remains on programme.
- Structural top-out is expected to take place in August with the official event to celebrate the major milestone in September 2023.
- Formwork strip out of the basement, ground and level 1 have been completed and service rough ins have commenced ahead of time.
- The anticipated completion date of the building remains mid-2024.
AVJennings is in advanced discussions with an operator for a lease on part of the ground floor tenancy and we hope to be able to announce some exiting news for the entire Waterline community shortly.
As always with construction, progress of works is subject to weather conditions, authority approvals and unforeseen impacts however, we will continue to keep everyone informed on a regular basis. Please continue to check the Waterline Place website for regular updates.