Aspect in Mernda

June 2022 Construction Update.

So much has been happening onsite at Aspect with plenty of progress being made on Stage 1 and 2 civils!

View the latest aerial footage below taken in late June 2022.

 

Key updates:

Stage 1

  • Underground services, concrete sleeper walls and kerbs complete
  • Footpaths and rock retaining walls to be installed

Stage 2

  • Crushed rock on roads complete
  • Underground services and concrete sleeper walls underway

 

Should you have any questions or queries about the construction progress of your land and or the Titles process, contact our Customer Service Officer - Silvana Johnson.

E: sjohnson@avjennings.com.au
P: 03 8888 4815

For all things Aspect, be sure to like our Facebook page @AspectAVJennings page to keep up to date with construction progress, events, promotional offers, things to do and regular local area information.